We are thrilled to announce the commencement of a new S278 Civils Works project on behalf of Redrow at Canute Place, Knutsford. This project includes the construction of a new roundabout, new carriageway, new footpaths, surfacing of the existing highway, and the installation of pedestrian guardrails.

The project will start on the 31st of July and is expected to take approximately 9 weeks to complete. The work will be split into 6 phases to ensure minimal disruption and efficient progress. Please see the phasing drawing below for detailed information on how the works will be carried out.

Phasing Drawings

We are excited to bring these improvements to the community and appreciate your patience and cooperation.

Traffic Management will be in place during the works for each of the phases, copies of these can be found below:

Phase 01– Gaskell Avenue / Kind Edward Road – 31/07/2024 to 09/08/2024

Phase 02 – Kind Edward Road Splitter – 09/08/2024 to 17/08/2024

Phase 03 – Footway King Edward Road & Canute Place Central Island – 17/08/2024 to 29/08/2024

Phase 04 – Footway Northwich Road / Manchester Road – 30/08/2024 to 04/09/2024

Phase 05 - Central Island – 05/09/2024 to 14/09/2024

Phase 06 - Carriageway – 17/09/2024 to 22/09/2024

Phase 06 - Resurfacing Diversions

News

Latest News Posts

Trafford Pedestrian and Cycling Improvements

Trafford Pedestrian and Cycling Improvements

Three major junction improvements will be completed on behalf of Trafford Council, taking us to Spring 2024. The project has seen ...

Read More >

Pilsworth Traffic Calming

Pilsworth Traffic Calming

Rochdale Borough Council, Rochdale Development Agency and George Cox are working in partnership to deliver the Pilsworth Road, HGV Mitigation ...

Read More >

Apprentices Celebrate Level 1 Ground Works Success

Apprentices Celebrate Level 1 Ground Works Success

We are thrilled to announce that our apprentices, Benedict Constant and Keith Watson, have successfully achieved their Level 1 Ground ...

Read More >

Our Accreditations