Canute Place, Knutsford
We are thrilled to announce the commencement of a new S278 Civils Works project on behalf of Redrow at Canute Place, Knutsford. This project includes the construction of a new roundabout, new carriageway, new footpaths, surfacing of the existing highway, and the installation of pedestrian guardrails.
The project will start on the 31st of July and is expected to take approximately 9 weeks to complete. The work will be split into 6 phases to ensure minimal disruption and efficient progress. Please see the phasing drawing below for detailed information on how the works will be carried out.
We are excited to bring these improvements to the community and appreciate your patience and cooperation.
Traffic Management will be in place during the works for each of the phases, copies of these can be found below:
Phase 01– Gaskell Avenue / Kind Edward Road – 31/07/2024 to 09/08/2024
Phase 02 – Kind Edward Road Splitter – 09/08/2024 to 17/08/2024
Phase 03 – Footway King Edward Road & Canute Place Central Island – 17/08/2024 to 29/08/2024
Phase 04 – Footway Northwich Road / Manchester Road – 30/08/2024 to 04/09/2024
Phase 05 - Central Island – 05/09/2024 to 14/09/2024